NextEra holds open house for $13B Fayette County power plant proposal

By Garrett Neese 7 min read
1 / 4
Denise Whetzel of McClellandtown and Elaine Whetzel of Luzerne Township look at a map of a proposed power plant with NextEra senior project manger Ryan Legge at an open house Tuesday night in Brownsville. [Garrett Neese]
2 / 4
About 200 Fayette County residents attended the first of three presentations on NextEra's proposed power plant in Luzerne Township at an open house on the project Tuesday night. [Garrett Neese]
3 / 4
Teddy Ivanco, director of development for NextEra, gives a presentation Tuesday on a proposed $13 billion power plant project in Fayette County. [Garrett Neese]
4 / 4
Fayette County residents 无毛视频 some cautiously optimistic, some skeptical 无毛视频 talked with NextEra representatives about enviromental impacts, site work and other aspects of a proposed $13 billion power plant in Fayette County at an open house Tuesday. [Garrett Neese]

Hundreds of people turned out for an open house in Brownsville Tuesday night about a proposed $13 billion power plant in Fayette County.

The 3.75-gigawatt East Riverside Energy Center would be located in Luzerne Township at the former site of the Isabella Mine.

无毛视频淚 think part of our development process is transparency with the community,无毛视频 said Alec Mazzuco, senior project manager for NextEra. 无毛视频淪o we voluntarily held this open house to facilitate any questions, comments, concerns regarding the East Riverside Energy Project.无毛视频

At the top of each hour, NextEra held a five-minute presentation in the auditorium where NextEra director of development Teddy Ivanco explained the basics of the project.

The three combined cycle natural gas power plants would be used to power a yet-to-be-determined large-scale industrial user. Because of space constraints, the plant will be built on about 150 acres of the 700-acre site.

NextEra was chosen for the development in March through a trade pact between the U.S. and Japan to develop energy infrastructure throughout the country. Funding for the power plant is coming from the U.S. Department of Commerce.

Power from the plant will be put on the grid for an undetermined large-scale industrial user, which will be chosen by the U.S. and Japan.

The power generated by the turbines will be placed on the grid and transferred to the eventual end user, which will be located off-site and might not be within Fayette County, NextEra said.

NextEra estimates 2,000 construction jobs will be created as the plant is built, and about 100 permanent jobs will be connected to the plant.

Renderings and other displays were set up around the perimeter of the Brownsville High School gymnasium. It was split into groups, including a map of the site, the environmental team, the permitting process, project overview and development and an explanation of the international trade deal behind the project.

Elaine Whetzel and Denise Whetzel were huddled around the project map. Property about an eighth of a mile from the site has been in their family for the past 200 years.

Both said they were concerned about the site无毛视频檚 effect on their land. Denise, who lives in McClellandtown but owns property near the site, said she worried emissions from the plant would be harmful to Elaine, who has respiratory issues.

无毛视频淲ith the family, we have 100 acres on both sides of the road,无毛视频 said Denise Whetzel. 无毛视频淲e无毛视频檝e always dreamed of putting a house there ourselves, but now I don无毛视频檛 know if I would want to.无毛视频

Learning more about the project had solidified their opposition, they said.

无毛视频淚 thought it was going to be closer to the river, and that would be a mile from me, and that was close enough,无毛视频 Elaine said. 无毛视频淚t无毛视频檚 ridiculous. It无毛视频檚 right there.无毛视频

Scott Huhn and Jamie Blaney, who live in Luzerne Township about half a mile from the proposed site, were worried about the disruption created by construction traffic.

无毛视频淲e get about three cars an hour, and you figure if there无毛视频檚 going to be 2,000 people working, there无毛视频檚 only two ways in,无毛视频 Huhn said.

Some residents backed the project, which they said would bring benefits to the area that has been strapped for resources.

无毛视频淟uzerne Township could use some progress,无毛视频 said Jim Ducar of Allison, who thought it could lead to better service in the county as well as generating taxes for communities, schools and volunteer fire companies.

无毛视频淩ight now, it无毛视频檚 pretty favorable,无毛视频 he said. 无毛视频淥ther than that, you have to wait and see a little bit while it progresses. So be careful because once you go across, you can无毛视频檛 go back.无毛视频

Others said it无毛视频檚 too early to tell whether it will benefit the county.

Jim Rosenberg of Redstone Township runs the Fayette Marcellus Watch website, which tracks oil and gas projects in Fayette County. The plant will have a 无毛视频渕ajor impact,无毛视频 he said.

Whether that无毛视频檚 good or bad will depend on a few things, he said.

If that energy winds up going to a data center, Rosenberg thinks it无毛视频檒l be a net negative for the county. He said it will also come down to permitting details, what kind of equipment they install and the type of noise remediation.

无毛视频淭here无毛视频檚 a lot that they have not been telling us,无毛视频 he said. 无毛视频淭hey haven无毛视频檛 chosen an equipment supplier for the turbines, so it无毛视频檚 difficult right now to have an exact set of numbers for the air quality impact.无毛视频

Centerville residents Kathleen McDonald and Candi Taylor came because of their worries over environmental concerns and potential impact on their electric and natural gas bills.

They said they would like to see a closed-loop system installed that would retain the 30 million gallons of water per day from the Monongahela that NextEra plans to use in cooling the plant.

Taylor said a NextEra representative she talked to had made compelling points about the projected need for more electrical generation over the next 50 years, particularly for goods like electric cars.

无毛视频淲e无毛视频檙e having blackouts here, and she said that this is going to help generate more electricity for us,无毛视频 she said. 无毛视频淚 hope it does, and I hope we don无毛视频檛 have to pay for it.无毛视频

State Rep. Charity Grimm Krupa, who represents Luzerne Township, said afterward the project could boost the natural gas industry and help fill the gap in energy production needed to offset recent plant closings as residential energy needs increase. At the same time, she said, they also need to be 无毛视频済ood stewards of the earth.

无毛视频淚 hope that we find a happy medium to make sure that we can move forward with this energy production and innovation while still being mindful of the environment,无毛视频 she said.

Grimm Krupa said the presentation had been vague in spots, and that she was disappointed it didn无毛视频檛 allot time for community members to ask questions. She wanted to know how many of the 100 jobs created would be filled remotely. Like McDonald and Taylor, she was also curious about where the natural gas powering the plant would come from.

无毛视频淚 was disappointed that they didn无毛视频檛 take questions and answers today, but hopefully moving forward, that无毛视频檚 something that they prioritize doing,无毛视频 she said.

Mazzuco said NextEra won无毛视频檛 be involved in the physical infrastructure that will provide the gas, but that the companies they无毛视频檙e working with are sourcing it from the Utica and Marcellus shales.

Fayette County commissioners said they thought the project was a landmark development for the county.

无毛视频淲e have been talking to people for the last four or five years about this prospect of generating power locally, so that we have an enhanced grid to be able to attract new business to Fayette County,无毛视频 Chairman Scott Dunn said. 无毛视频淪o we无毛视频檙e excited.无毛视频

Commissioner Harry Kaufman sees the project as part of an upswing for the county, building on recent manufacturing expansion.

无毛视频淲e welcome investment in Fayette County, and of course, investment that is quality investment means even more,无毛视频 he said. 无毛视频淪o this is a quality investment that is going to help grow Fayette County.无毛视频

Responding to concerns from residents about nondisclosure agreements, Dunn said the commissioners had signed NDAs with Fay-Penn Economic Development Council to work collaboratively on bringing new business to the county, but had not signed anything with NextEra or any data center developer.

Dunn and Vice Chairman Vince Vicites said the county will be working on community benefit agreements that ensure NextEra provides funding for local community resources.

无毛视频淭hey无毛视频檙e willing to do that, being that they are coming here and are going to be our neighbors here,无毛视频 Vicites said. 无毛视频淭hey want to invest in the county. We无毛视频檙e going to work with them to develop those agreements so people, the county, can get millions of dollars of investment into the county.无毛视频

NextEra will conduct studies and other site assessments through mid-2027 to gauge the feasibility and environmental impact of the plant. A timeline shown at the open house estimates the permitting process for all phases of the plant will take until the middle of 2030.

NextEra is eyeing a construction start of late 2027 for the plant, which would go online in phases between 2030 and 2032.

CUSTOMER LOGIN

If you have an account and are registered for online access, sign in with your email address and password below.

NEW CUSTOMERS/UNREGISTERED ACCOUNTS

Never been a subscriber and want to subscribe, click the Subscribe button below.

Starting at /week.